A Realistic Timeline for Your Home Build: Milestones from Brief to Handover

August 24, 2026 · Heather Elliott · 3 min read

A Realistic Timeline for Your Home Build: Milestones from Brief to Handover, CK Construction, builders in Redditch, Birmingham, Solihull and Warwickshire

The most common question we get, after cost, is “how long will the whole thing take?” The honest answer is: longer than you think, but less than you fear if you understand the milestones. Here is a realistic timeline for a typical home extension project with CK Construction in Redditch, Birmingham or Solihull.

Phase 1, Brief and feasibility (2-3 weeks)

  • Free initial site visit (we come to you, no obligation)
  • Discussion of your brief, budget, timescales
  • Advice on planning route (Permitted Development vs full planning)
  • Rough budget estimate (“ballpark figure”) so you know whether to proceed

Phase 2, Design and planning (4-14 weeks)

The spread is wide because it depends on planning route.

  • Measured survey of the existing property: 1 week
  • Design iterations with architect: 2-4 weeks
  • Planning application preparation: 1-2 weeks
  • Planning determination: 8-10 weeks statutory (if full planning needed)
  • Building Regulations drawings and structural calculations: runs alongside planning

Phase 3, Pre-start (3-4 weeks)

  • Fixed-price quote finalised against detailed drawings
  • Contract signed, deposit paid
  • Party Wall notices served if applicable (two months before start)
  • Building Control application
  • Material lead-times ordered (steels, windows, kitchen)

Phase 4, Construction (varies)

Realistic on-site durations for typical projects:

  • Single-storey rear extension (20-30 m²): 10-14 weeks
  • Two-storey rear extension: 16-22 weeks
  • Wrap-around extension: 14-18 weeks
  • Loft conversion with dormer: 8-12 weeks
  • Full new build detached home: 36-52 weeks
  • Whole house refurbishment: 16-26 weeks

Key construction milestones

  1. Groundworks and foundations. First Building Control inspection on foundations.
  2. Oversite and DPC. Insulation and damp proof course laid, slab poured.
  3. Shell up. Walls built to plate height, steel beams installed, roof structure framed.
  4. Weathertight. Roof covering on, windows and external doors fitted. From this point internal works continue in any weather.
  5. First fix. Electrics, plumbing and heating pipework installed in walls and floors.
  6. Plastering. All walls and ceilings skimmed.
  7. Second fix. Sockets, switches, radiators, sanitaryware fitted. Kitchen installed.
  8. Finishes. Decoration, flooring, final cleaning.
  9. Snagging. Walk-through with the client, snag list raised, all items closed within one week.
  10. Handover. Keys, warranty paperwork, Building Control completion certificate.

What causes delays?

  • Weather during foundation stage (we plan starts around expected weather)
  • Client changes mid-build (one of the biggest causes of overruns, worth deciding early and sticking to the plan)
  • Material lead-times on bespoke items (specify early)
  • Discovered conditions in older properties (hidden damp, rotten joists, poor existing foundations)

How we keep you informed

Every CK Construction project gets a dedicated project manager, a weekly written progress update by email, and site-visit access by prior arrangement. You always know where you are in the programme.

Thinking about starting a project? Call 01527 521835 or use the contact form for a free initial site visit.

Ready to start your build?

Tell us about your project and we will get back to you within one working day.

Request a quote Call 01527 521835